Tesco Metro Birmingham

30. April 2021 | All articles, Projects /

ROXSTAcube – compact CO2 solution for small footprints

When we approached a project in Birmingham, England, we were faced with some specifics on site including small footprint, central city area and weight limitations for the unit (crane loading). Thanks to our compact CO2 solution ROXSTAcube, we were able to realize and deliver the performances required by our customer Carter Synergy within a very short time. The project was successfully completed and in the future two of our CO2 solutions will provide the right amount of cooling for a local Tesco Metro supermarket.


The store takes up the basement, ground and first floors of a seven-story building, with the roof identified as the only solution to site any new refrigeration plant which was required for the project. The location of the store, deep within the city centre also proved challenging due to exceptionally narrow roadways and heavily restrictive access.

During the design phase, it was identified that the plant had to be built as a customised solution within an exceptionally tight timeframe to achieve the programme. Partly due to the need to crane the new refrigeration plant onto the roof and into position and the fact the access for the crane was so restrictive. Essentially, the development of a solution with a specific weight profile to meet the maximum crane size that could be placed into position close enough to the building and given that this then had to negotiate a 40m horizontal reach.

Many challenges – one solution: ROXSTAcube

Shaun Law, Business Development Design Principal at Carter Synergy: “To achieve these challenges, we approached TEKO Refrigeration – one of our clients specified plant providers – who immediately supported us with the relevant design and achieved the build of two, transcritical CO2 pack units in a very tight timeframe. This whilst supplying solutions that met the refrigeration design criteria, customer specification and weight characteristics (Sub 2200 Kg’s per unit). The two units supplied were 1 MT only (48.2 kW @ t0 -7 °C) and 1 MT & LT unit (MT 85.3 kW @ t0 -7 °C & LT 6.9 kW @ t0 -34 °C). This new plant replaced the 3 housed HFC packs which had been in operation since 2004.”

Insertion with obstacles

Once the required road closures had been organized and the crane positioned, the transport team began the process of erecting and preparing for the lift.Unfortunately, the first snow of the year promptly started to fall, and the planned lift had to be cancelled. Thankfully, the team worked hard to ensure the removal of the three aged packs went ahead.

A second lift then had to be arranged as soon as possible and the new systems were then lifted into place without further incident within a week.

“The project required a real collaborative effort, and the successful completion was only achieved due to the support and professionalism of all involved.” – Shaun Law

 

  Sarah Schröter

You might also be interested in

Availability between Christmas and New Year

2021 was a real exciting and challenging year for all of us. Christmas is just around the corner and the turn of the year is also within reach. Therefore, we would like to take this opportunity to say THANK YOU for being our valued partner, filled with trust and commitment. We are there for you… […]
23. December 2021

Extension of the TEKO R&D Test Laboratory

Report by Andreas Schmitt (Head of Research & Development) and Lukas Beier (Technology Development) The history of industrial refrigeration technology has been shaped by many attempts to render commercial refrigeration efficient. In addition to various unit constellations, different refrigerants and refrigerant mixtures have been used. After almost 150 years of industrial refrigeration, a serious intervention […]
16. December 2021

ENT-TRO: New specialists for the refrigeration industry

Interview with ENT-TRO GmbH Skilled workers in the refrigeration industry are in short supply. The job description for Mechatronics Technician for refrigeration technology is poorly known and does not exactly rank in top position for apprenticeships in demand. So we, in the industry, still have our work cut out to improve this situation. Our long-term […]
16. December 2021

Trade Fairs 2021

We were not expecting any live events in 2021. And then suddenly three trade fairs, which had originally been planned for 2020, took place in November. Refrigera, Bologna We started with Refrigera in Bologna from 3rd to 5th of November. The event revolved around everything related to the entire production chain of industrial, commercial and […]
16. December 2021

ROXSTA G6 cools Carrefour E-Commerce-Center

For Belgian consumers, e-commerce in groceries is not just a coronavirus-related trend, but has become a genuine habit. In response to this exponential growth, Carrefour Belgium announced in September 2020 that it had entered into an exclusive partnership with international company Food-X Technologies Inc. in order to benefit from their cutting-edge software. By 2026, Carrefour […]
16. December 2021

Wurm Systeme – Procurement crisis

Article from the Wurm magazine FRESH UP 02 2021 (published in summer 2021) >> FRESH UP 02 2021 << Ongoing procurement crisis for materials and components is also affecting our production facility In fact, the material bottlenecks for components, raw materials and accessories have occurred at a level far exceeding past cyclical waves of demand (allocation). There […]
16. December 2021