Tesco Metro Birmingham

30. April 2021

ROXSTAcube – compact CO2 solution for small footprints

When we approached a project in Birmingham, England, we were faced with some specifics on site including small footprint, central city area and weight limitations for the unit (crane loading). Thanks to our compact CO2 solution ROXSTAcube, we were able to realize and deliver the performances required by our customer Carter Synergy within a very short time. The project was successfully completed and in the future two of our CO2 solutions will provide the right amount of cooling for a local Tesco Metro supermarket.


The store takes up the basement, ground and first floors of a seven-story building, with the roof identified as the only solution to site any new refrigeration plant which was required for the project. The location of the store, deep within the city centre also proved challenging due to exceptionally narrow roadways and heavily restrictive access.

During the design phase, it was identified that the plant had to be built as a customised solution within an exceptionally tight timeframe to achieve the programme. Partly due to the need to crane the new refrigeration plant onto the roof and into position and the fact the access for the crane was so restrictive. Essentially, the development of a solution with a specific weight profile to meet the maximum crane size that could be placed into position close enough to the building and given that this then had to negotiate a 40m horizontal reach.

Many challenges – one solution: ROXSTAcube

Shaun Law, Business Development Design Principal at Carter Synergy: “To achieve these challenges, we approached TEKO Refrigeration – one of our clients specified plant providers – who immediately supported us with the relevant design and achieved the build of two, transcritical CO2 pack units in a very tight timeframe. This whilst supplying solutions that met the refrigeration design criteria, customer specification and weight characteristics (Sub 2200 Kg’s per unit). The two units supplied were 1 MT only (48.2 kW @ t0 -7 °C) and 1 MT & LT unit (MT 85.3 kW @ t0 -7 °C & LT 6.9 kW @ t0 -34 °C). This new plant replaced the 3 housed HFC packs which had been in operation since 2004.”

Insertion with obstacles

Once the required road closures had been organized and the crane positioned, the transport team began the process of erecting and preparing for the lift.Unfortunately, the first snow of the year promptly started to fall, and the planned lift had to be cancelled. Thankfully, the team worked hard to ensure the removal of the three aged packs went ahead.

A second lift then had to be arranged as soon as possible and the new systems were then lifted into place without further incident within a week.

“The project required a real collaborative effort, and the successful completion was only achieved due to the support and professionalism of all involved.” – Shaun Law

 

  Sarah Schröter

You might also be interested in

PREMIERE IN SWEDEN: TEKO AT THE NORDBYGG EXHIBITION IN STOCKHOLM

TEKO will be represented in Sweden for the first time at the Nordbygg exhibition in Stockholm. Visitors are invited to visit the TEKO team from April 23rd to 26th at booth A16:52. Nordbygg is the largest meeting place for the Nordic construction industry and attracts visitors from across Scandinavia, the Baltic States, and Europe every […]
24. April 2024

SUCCESSFUL INDUSTRIAL PROJECT IN THE NETHERLANDS!

On 7,000 m², concentrated technical expertise for the benefit of the environment! Together with partners MUR Conditioning and TEKO, Wurm GmbH & Co. KG – Electronic Systems has once again achieved something great. This time for the renowned hotel chain Van der Valk in the Netherlands. For the new distribution center of the prestigious hotel […]
20. March 2024

BETWEEN INNOVATION AND IMPLEMENTATION: AN INTERVIEW WITH ROLF SCHMIDT – ENERGY EFFICIENCY MANAGER OF THE REWE GROUP

Rolf Schmidt is a dedicated visionary who is committed to actively shaping the future. He has successfully leveraged his extensive experience and network in the field of refrigeration technology to collaborate with companies Wurm GmbH & Co. KG Elektronische Systeme and TEKO to not only develop innovative ideas, but also to implement them into successful products. To […]
14. March 2024

Innovative solution for refrigerated plug-in cabinets

Seco‘s FridgiWise Module Seco has been providing service for plug-in cabinets for more than two decades. In recent years, the company has observed the increasing use of plug-in cabinets for cooling high-end products, such as sushi. To better coordinate the more than 2 million chests in service and the 200 service technicians in operation, Seco […]
7. March 2024

ROXSTASMART

INNOVATIVE TECHNOLOGY FOR THE REFRIGERATION SYSTEMS TEKO has developed the TECO2nditioner. This is installed to protect the compressor from damage and significantly extend its lifespan. The technology ensures that the compressor‘s suction temperatures are reduced and kept constant, preventing the oil used for lubricating the compressor from getting too hot. Compared to the commonly used […]
27. February 2024

TEKOPOST IS BACK!

We are excited to announce that the customer magazine TEKOPOST is back! Dive into exciting articles and discover: A look behind the scenes: Exciting insights into the TEKO world. Expert interview with Rolf Schmidt from REWE Group about the collaboration. Brand new machining center: State-of-the-art technology for highest precision. Don’t miss the opportunity to read […]
22. February 2024